We know that,
Manpower x working hour x 60 x Efficiency
Target=…………………………………………………………………
SMV
90 x 10 x 60
=………………………….
32
54000
=………………………
32
= 1687 pcs (100% Target) (Answer)
Again,
Manpower x working hour x 60 x Efficiency
Target=……………………………………………………………
SMV
90 x 10 x 60 x 0.70
=……………………………………
32
37800
=……………………………
32
= 1121 pcs (70% Target) (Answer)