We know that,
Manpower x working hour x 60 x Efficiency%
Target=…………………………………………………………………………
SMV
80 x 8 x 60 x 0.50
=………………………………………..
25
19200
=…………………….
25
= 768 pcs
Order quantity
Need day for complete this order for single line= …………………………………
Per day capacity
50000
=………………………
768
= 65.10 day (Answer)