Garments education always share about IE, Planning, Merchandising, Production, Quality, Washing, IE Math Solution and garments industry related content. Here I discussed about smv, sam, work study, method study, motion study, work measurement, time study, production sop,operation breakdown, Ie responsibility, thread consumption, ie math question sotution, costing, cutting sop, Job responsibility, quality, quality sop, cutting defect, sewing defect, study work, six sigma, 7 Qc, 7 wastage, 6s etc

Sunday, June 18, 2023

IE math question: Suppose style SMV 25, Manpower 80, working hour 8, order quantity 50000 pcs, average efficiency 50%, Then how may day you will set in schedule to complete the quantity?

Here I discuss about ie math question. If you pay attention my math solution then you can easily solve math question.
Solution:

 We know that,

                              Manpower x working hour x 60 x Efficiency%

   Target=…………………………………………………………………………

                                                           SMV

 

                            80 x 8 x 60 x 0.50

             =………………………………………..

                                        25

 

                      19200

             =…………………….

                          25

 

              = 768 pcs

 

                                                                                         Order quantity

Need day for complete this order for single line= …………………………………

                                                                                         Per day capacity

 

                                                                                      50000

                                                                          =………………………

                                                                               768

                                                                          = 65.10 day (Answer)