Garments education always share about IE, Planning, Merchandising, Production, Quality, Washing, IE Math Solution and garments industry related content. Here I discussed about smv, sam, work study, method study, motion study, work measurement, time study, production sop,operation breakdown, Ie responsibility, thread consumption, ie math question sotution, costing, cutting sop, Job responsibility, quality, quality sop, cutting defect, sewing defect, study work, six sigma, 7 Qc, 7 wastage, 6s etc

Sunday, June 18, 2023

IE math question: Line target 1200, process SMV 0.45 and working min 600, then find out the process operator requirement.

Here I discuss about ie math question. If you pay attention my math solution then you can easily solve math question.
Solution:

Given that,

Process SMV 0.45, then Target= 60/SMV

                                                  =60/.45

                                                   =133 pcs

 Working hour= working min/60

                      =600/60

                      =10 hour

 Per hour line target= 1200/10

                                =120 pcs

 Now,

 Requirement operator= 120/133

                                    =0.90 operator. (Answer)