Garments education always share about IE, Planning, Merchandising, Production, Quality, Washing, IE Math Solution and garments industry related content. Here I discussed about smv, sam, work study, method study, motion study, work measurement, time study, production sop,operation breakdown, Ie responsibility, thread consumption, ie math question sotution, costing, cutting sop, Job responsibility, quality, quality sop, cutting defect, sewing defect, study work, six sigma, 7 Qc, 7 wastage, 6s etc

Sunday, June 18, 2023

IE math question: Order quantity 20000 pcs, manpower 33, SMV 17, working hour 10, achievement 80% of customer demand, and then how many days need to complete the order quantity?

Here I discuss about ie math question. If you pay attention my math solution then you can easily solve math question.
Solution:

We know that,

 

                        Manpower x working hour x 60 x Efficiency%

   Target=…………………………………………………………………

                                                    SMV

 

                    33 x 10 x 60 x 0.8

             =………………………………

                           17

 

                         15840

             =………………………

                          17

 

   = 931.76

            =932 pcs

                                                                                        Order quantity

Need day for complete this order for single line = ……………………………

                                                                                       Per day capacity

 

                                                                                          20000

                                                                           =………………………

                                                                                           932

 

                                                                            = 21.45 day (Answer)