Garments education always share about IE, Planning, Merchandising, Production, Quality, Washing, IE Math Solution and garments industry related content. Here I discussed about smv, sam, work study, method study, motion study, work measurement, time study, production sop,operation breakdown, Ie responsibility, thread consumption, ie math question sotution, costing, cutting sop, Job responsibility, quality, quality sop, cutting defect, sewing defect, study work, six sigma, 7 Qc, 7 wastage, 6s etc

Sunday, June 18, 2023

IE math question: Stitch length 38 inches, SPI 9, Machine RPM 3400 and production per hour 80 pcs then calculate NDT?

Here I discuss about ie math question. If you pay attention my math solution then you can easily solve math question.
Solution:

NDT mean needle down time also called needle up & down going time or needle running time.

Total stitch= SPI x Seam length

      = 9 x 38

                 =342 stitch

 Produce stitch= 342 x 80

                        =27360 stitch

  Machine time= RPM x 60

                       =3400 x 60

                       =204000


                 Produce stitch

NDT=……………………….. x100

                 Machine time

  

                  27360

       =…………………… x100

                 204000

 

                2736000

       =……………………

                204000

 

       = 13.41%  (Answer)