Given that,
Order quantity= 500 Dozens x 12
=6000 pcs
We know that,
Manpower x working hour x 60 x Efficiency%
Target=………………………………………………………………
SMV
10 x 10 x 60 x 0.75
=……………………………………….
12.6
4500
=…………………….
12.6
Production= 357.14 pcs per day.
Order quantity
Day need=………………………………
Per day capacity
6000
=………………….
357.14
= 16.80 days (Answer)
Solution: (B)
6000
If we want to complete in 14 day then per day production need =………………..
14
= 428.57 pcs
357.14
10 Girls capacity per hour=…………………
10
= 35.71 pcs
428.57
So per day hour need=………………
35.71
= 12 hour.
So, Need per day 12 hour work each girls for complete this order in between 14 day. (Answer)