Output=1600
SMV=20
Efficiency=70%
Working hour=?
We know that,
Output x SMV
Working hour=…………………………………………
Manpower x 60 x Efficiency
1600 x 20
=…………………………………
65 x 60 x 0.70
32000
=………………………
2730
=11.72 Hour (Answer)
Garments education always share about IE, Planning, Merchandising, Production, Quality, Washing, IE Math Solution and garments industry related content. Here I discussed about smv, sam, work study, method study, motion study, work measurement, time study, production sop,operation breakdown, Ie responsibility, thread consumption, ie math question sotution, costing, cutting sop, Job responsibility, quality, quality sop, cutting defect, sewing defect, study work, six sigma, 7 Qc, 7 wastage, 6s etc