Garments education always share about IE, Planning, Merchandising, Production, Quality, Washing, IE Math Solution and garments industry related content. Here I discussed about smv, sam, work study, method study, motion study, work measurement, time study, production sop,operation breakdown, Ie responsibility, thread consumption, ie math question sotution, costing, cutting sop, Job responsibility, quality, quality sop, cutting defect, sewing defect, study work, six sigma, 7 Qc, 7 wastage, 6s etc

Sunday, June 18, 2023

IE math question: If takt time 40 min, manpower 50, Allowance 7%, BPT 0.75, working hour 10, bottleneck 1.25 then find out (A) Worker performance% and (B) Line balancing%

Here I discuss about ie math question. If you pay attention my math solution then you can easily solve math question.
Solution:

SMV= (Manpower x BPT) + Allowance

     = (50 x 0.75) + 7%

     = 37.5 + 7%

     = 40.12 min

                                           Manpower x working hour x 60

SMV based production=……………………………………………

                                                               SMV

 

                                     50 x 10 x 60 

                          = ……………………………..

                                            40.12

 

                                    30000

                               =………………..

                                     40.12

 

                          = 748 pcs

 

                                                     50 x 10 x 60

Takt time based production=…………………………

                                                           40

 

                                            30000

                                           =………………………

                                                         40

 

                                           =750 pcs

 

                             SMV based production

Performance=………………………………………

                           Takt time based production

 

                                  748

                     =…………………. X100

                                 750

 

                     =99.73% (Answer)

 

                                        BPT

Line balancing=…………………………………… x100

                              Bottleneck + Allowance

 

                                     0.75

                       =…………………………. x100

                                   1.33+7%


                                         0 .75

                        =………………………. x100

                            1.3375

                             

                         = 56.07% (Answer)