SMV= (Manpower x BPT) + Allowance
= (50 x 0.75) + 7%
= 37.5 + 7%
= 40.12 min
Manpower x working hour x 60
SMV based production=……………………………………………
SMV
50 x 10 x 60
= ……………………………..
40.12
30000
=………………..
40.12
= 748 pcs
50 x 10 x 60
Takt time based production=…………………………
40
30000
=………………………
40
=750 pcs
SMV based production
Performance=………………………………………
Takt time based production
748
=…………………. X100
750
=99.73% (Answer)
BPT
Line balancing=…………………………………… x100
Bottleneck + Allowance
0.75
=…………………………. x100
1.33+7%
0 .75
=………………………. x100
1.3375
= 56.07% (Answer)