Garments education always share about IE, Planning, Merchandising, Production, Quality, Washing, IE Math Solution and garments industry related content. Here I discussed about smv, sam, work study, method study, motion study, work measurement, time study, production sop,operation breakdown, Ie responsibility, thread consumption, ie math question sotution, costing, cutting sop, Job responsibility, quality, quality sop, cutting defect, sewing defect, study work, six sigma, 7 Qc, 7 wastage, 6s etc

Thursday, June 15, 2023

IE math question: If a line machine SMV 14.70 min., helper SMV 5.80 min., working hour 10, hourly production 150 pcs, efficiency 70% and other worker 65 then find out how much helper use in the line?

Here I discuss about ie math question. If you pay attention my math solution then you can easily solve math question.
Solution:

 Total SMV= 14.70 + 5.80

                  = 20.5 min.

 Production= 150 x 10

                   = 1500 pcs.

 We know that,

                               Production x SMV

Manpower=………………………………………………..

                        Working hour x 60 x Efficiency

 

                  1500 x 20.5

               =…………………………….

                             10 x 60 x 0.7

 

                30750

               =………………………

                              420


Manpower= 73.21

 

      Helper= 73.21 – 65

             = 8.21

             = 8 (Answer) 